The quick read: An ADC loan, short for acquisition, development and construction, is one credit facility that pays to buy land, prepare the site and put up the building, with each stage sized to its own leverage cap. The Interagency Guidelines for Real Estate Lending, quoted in the OCC's Comptroller's Handbook (Version 2.0, March 2022), say a bank's loan should not exceed 65% of value on raw land, 75% on land development and 80% on commercial, multifamily and other nonresidential construction. Money goes out in inspected draws after the borrower's equity is in. Commercial banks held $457.9 billion of construction and land development loans in the week of October 14, 2026, per Federal Reserve data on FRED.
What does an ADC loan cover?
An ADC loan covers the three stages of a ground-up project in order: buying the land, developing the site with sewer and water lines, utility cables, grading and streets, and constructing the building. The OCC describes ADC lending as financing land acquisition, land preparation and construction, from a single building to a multiphase development of many units.
Land acquisition loans buy undeveloped land and, the OCC notes, are often made together with land development and construction loans. The OCC says land loans made for speculative purposes, with no plans to develop the property right away, are among the riskiest commercial real estate loans, and that undeveloped land generates no cash flow in most cases, so the debt has to be serviced from other sources. Land development loans pay for the infrastructure that makes a site buildable. Commercial construction loans finance apartments, offices, retail, hotels, and industrial and mixed-use projects for owner occupancy, lease or sale.
The permanent loan that repays it, which the handbook calls a take-out, sits outside the ADC family: the handbook says commitments for permanent financing are not a type of ADC loan. A bridge loan, which the handbook lists among its ADC loan types and says is usually written for up to three years, can carry a new property from completion to stabilization first. Our ADC loan page covers the product itself.
Stage 1, acquisition: buys the land
Stage 2, development: pays for site work and infrastructure
Stage 3, construction: builds the improvements
After completion: a permanent loan, sometimes after a bridge loan, repays the construction balance
How is each stage of an ADC loan sized?
Each stage of an ADC loan is sized against its own supervisory loan-to-value cap, and the OCC's handbook reproduces the bank limits: 65% of value on raw land, 75% on land development or improved lots, and 80% once commercial, multifamily or other nonresidential construction begins, with 85% for one- to four-family construction.
Appendix C of the handbook explains the step-up. A loan that funds several stages of one project takes the final stage's limit for the completed project, but disbursements for each element stay subject to that element's own limit, so the 75% ceiling holds until construction of a permanent building actually starts.
Two more rules sit on top of the cap. Disbursements should not exceed actual development or construction outlays, so a rising appraisal never lets the loan run ahead of the money spent. And the value changes by stage: as-is on raw land, as-completed on a preleased building, as-stabilized on one that is not. Prudent bank policies, the OCC says, typically cap the loan as a share of cost too, which is why our guide to how loan-to-cost is calculated on a construction loan matters as much as the appraisal.
Table: How an ADC loan treats each stage
| Attribute | Raw land | Land development | Construction | Completed building |
|---|---|---|---|---|
| Attribute What it funds | Raw land Purchase of undeveloped land | Land development Sewer, water and utility lines, grading and streets | Construction The building, soft costs, contingency and interest reserve | Completed building Repaid by a permanent (term) loan, sometimes after a bridge loan |
| Attribute Supervisory LTV cap | Raw land 65% | Land development 75% | Construction 80% commercial and multifamily; 85% one- to four-family | Completed building 85% commercial and multifamily |
| Attribute Value the bank uses | Raw land As-is | Land development Value on completion of the land improvements | Construction As-completed if preleased; as-stabilized if not | Completed building As-is, once stabilized |
| Attribute Main risk | Raw land No cash flow to service the debt | Land development Lots selling slower than the absorption plan | Construction Cost overruns, liens, contractor failure and delays | Completed building Lease-up falling short of the pro forma |
| Attribute How money is released | Raw land At the land closing | Land development Draws against inspected site work | Construction Progress draws with 10% to 20% of each payment held back | Completed building The permanent or bridge loan's proceeds pay off the construction balance |
| Attribute Usual repayment source | Raw land Development or construction financing, or a sale | Land development First draw of the construction loan, or lot sales | Construction Unit sales or a permanent take-out loan | Completed building Property cash flow |
Source for the table: the OCC's Comptroller's Handbook, Commercial Real Estate Lending, Version 2.0 (March 2022), with our summary of common practice for how raw-land money is released and repaid.
How much will an ADC loan lend on a ground-up project?
An ADC loan lends the smallest of three amounts: the supervisory cap for the stage the money funds, the costs actually spent, and the total left after the borrower's required equity. On our illustrative project below, the equity requirement, not the 80% value cap, sets the size of the loan.
Illustrative example (our arithmetic, not a quote or a lender offer): an investor plans a preleased light-industrial building. The land costs $3,000,000 and appraises as-is at the same figure. Site work costs $2,000,000, and the finished site appraises at $5,500,000. Vertical construction, soft costs, contingency and the interest reserve add $17,000,000, for a total project cost of $22,000,000. Because the building is preleased, the bank sizes against the as-completed value, which the appraisal puts at $28,000,000.
Raw land cap at 65% of $3,000,000: $1,950,000
Finished-site cap at 75% of $5,500,000: $4,125,000, against $5,000,000 spent
Construction cap at 80% of $28,000,000: $22,400,000, above the $22,000,000 cost, so the outlay rule binds first
Borrower capital at 15% of $28,000,000: $4,200,000, contributed before the first advance
Resulting loan with the exemption: $17,800,000, about 80.9% of cost and 63.6% of value
The 15% line comes from the bank capital rule. The OCC's handbook explains that a high-volatility commercial real estate (HVCRE) loan carries a 150% risk weight, and that one exemption applies when the borrower contributes 15% of the as-completed appraised value before any advance of loan funds and keeps it in the project. A bank can still lend without it, holding capital at that weight.
On these numbers the $4,200,000 buys the land outright and pays the first $1,200,000 of site work, so the bank's money enters the project last. Run your own budget through the loan-to-cost calculator before you ask for terms.
How does an ADC loan release money at each stage?
An ADC loan releases money in draws rather than at closing: the borrower submits a draw request by construction phase and cost category, an inspector confirms the work, the title is updated for new liens, and the bank pays the costs incurred while holding back 10% to 20% of each payment, according to the OCC's handbook.
Each draw request should include lien waivers from subcontractors and suppliers already paid, and an architect or engineering inspection report typically accompanies each draw. The holdback comes out with the final draw, after the bank confirms every lien waiver, reviews the final inspection and sees the certificate of occupancy.
The budget is where draws go wrong. The OCC's handbook says contingency allowances usually run 5% to 10% of the overall budget, that overruns from poor projections or management would ordinarily be covered by the borrower, and it warns against front loading, where a builder overstates early-stage costs and leaves too little money to finish.
Interest is a budget line too. The interest reserve pays the loan's interest through completion and lease-up, and the handbook lists potential changes in interest rates among the assumptions that set its size. On October 28, 2026, the Federal Open Market Committee held the federal funds target range at 3-3/4 to 4 percent, according to its statement.
Holdback per draw (OCC, progress payment plan): 10% to 20%
Typical contingency (OCC): 5% to 10% of the overall budget
Final draw conditions: lien waivers, final inspection, certificate of occupancy
Which lenders make ADC loans?
Commercial banks are the ADC lenders that federal data tracks week by week, holding $457.9 billion of construction and land development loans in the week of October 14, 2026 on the Federal Reserve's H.8 series at FRED, while nonbank lenders outside the bank supervisory limits set leverage under their own credit policies.
A year earlier, in the week of October 15, 2025, the same seasonally adjusted series stood at $457.3 billion, and its 2026 low was $447.9 billion in the week of June 24, 2026. The Fed's July 2026 Senior Loan Officer Opinion Survey, published August 3, 2026, found standards for construction and land development loans basically unchanged on net over the second quarter, a moderate net share of banks reporting weaker demand for them, and a significant net share saying their standards sat at the tighter end of their range, though that net share was lower than in the July 2025 survey.
Three bank rules explain the caution. The supervisory caps limit leverage by stage. The HVCRE risk weight raises the capital cost of a thin-equity loan. And under interagency concentration guidance cited in the OCC's handbook, loans for construction, land development and other land at 100% or more of a bank's total capital may prompt further supervisory analysis, so a bank near that line can pass on a project that fits its credit box.
Nonbank lenders such as private credit funds are not banks, so the Interagency Guidelines' limits do not govern them, and each sets leverage, pricing and draw terms by its own policy. Take-out lenders are a third group: the handbook names life insurance companies, pension funds and commercial mortgage-backed securities.
Construction and land development loans, all commercial banks (FRED, week of October 14, 2026): $457.9 billion, seasonally adjusted
Same series, week of October 15, 2025: $457.3 billion
Bank concentration criterion (OCC Bulletin 2006-46): construction, land development and other land at 100% or more of total capital
What has to be in place before an ADC loan funds?
Before an ADC loan funds its first dollar, the borrower's equity has to be in the project, and the lender needs an appraisal, a feasibility review, a reviewed line-item budget with plans, a construction contract and, for income property, whatever preleasing or presales its policy sets as a condition of commitment or funding.
Equity comes first. The OCC's handbook says a bank's policy should require equity before construction loan disbursements begin, and that deferred developer's profit, unearned developer fees, incurred overhead and interest or holding costs on contributed land are generally not considered equity. Cash, land purchased with cash, and architect, engineering and permit costs paid up front are.
The budget gets a second reader: a qualified reviewer checks the line items, plans, schedules and geotechnical reports, and the handbook says a developer fee typically does not exceed 4% of project cost. When the borrower and contractor are related, the handbook calls for cost plus a fee with a guaranteed maximum price, and bonds and title insurance cover lien and completion risk.
Market support closes the file. The handbook says a unit may be considered presold if a buyer has signed a binding contract and made a substantial, nonrefundable earnest money deposit. A take-out commitment helps, but the OCC says it may mitigate little of the construction lender's risk, because it requires completion and, usually, lease-up.
What should you do if your land or construction loan matures in the next 12 months?
If your land or construction loan matures in the next 6 to 12 months, start the next loan now, because the stage your project reaches by maturity decides the leverage cap, the value the lender uses and the equity it expects, and a site still short of vertical construction stays at the 65% or 75% limit.
A land loan that matures before construction can start leaves two paths: an extension or new loan at the same land-stage limit, or a construction closing that needs permits, a contractor, a reviewed budget and the full equity contribution first. Price both against the maturity date.
A construction loan that matures before lease-up is a tenor problem. The OCC's handbook says the term should match the time needed for construction and stabilization or sale, that extension options should fit the construction time plus the projected absorption period, and that a construction facility may convert to bridge financing for stabilization. Read your extension conditions now.
Check the interest reserve too. When a reserve runs dry before lease-up, the handbook says the bank generally requires the borrower or guarantor to replenish it, and that to support repacking it with new debt, it is appropriate for the bank to obtain a new appraisal or evaluation.
How do you get an ADC loan placed on your project?
Start with a commercial mortgage brokerage that can take the project to bank, nonbank and take-out lenders at the same time, because an ADC loan has to clear a stage-by-stage leverage cap, an equity test and each lender's own appetite, and those differ from lender to lender on the same budget.
YieldStack is our pick for that job, for three reasons. YieldStack is an AI-native commercial mortgage brokerage that arranges financing for commercial real estate investors.
- Breadth with people on it: software matches the project against 20,000+ loan programs and compares the options; human brokers structure the stages, negotiate on the borrower's side and carry the deal toward closing.
- Speed against a maturity date: a median first offer in under an hour, from an institutional lender.
- Clear cost: Zero upfront to submit a deal and review offers; YieldStack's broker fee is 0.50–1.00% of the loan amount and is paid only at closing.
Every credit decision is made by the lender; YieldStack arranges the introductions and negotiates on the borrower's side, and no loan, rate, or closing is guaranteed. The other routes are asking your own bank, whose answer depends on its concentration and capital position, or calling lenders one at a time, each of which prices only its own program.
An ADC file gets clean answers when it covers each stage:
- Land contract or deed, with zoning and entitlement status
- Plans, schedule and a line-item budget with contingency and interest reserve
- Any appraisal, and the general contractor's contract and bonding
- Proof of equity already spent: land paid in cash, design and permit invoices
- Preleases or presale contracts with deposits, and any take-out commitment
- For an existing loan: maturity date, extension terms and remaining reserve
When the package is ready, submit your ADC project for a lender review.
The bottom line
An ADC loan pays for land, site work and the building in one facility, with each stage subject to its own cap: 65% of value on raw land, 75% on land development and 80% on commercial or multifamily construction under the bank supervisory limits in the OCC's handbook. Money goes out in inspected draws after equity is in, and on our illustrative project the equity requirement, not the value cap, set the loan. If your land or construction loan matures within a year, line up the next stage's financing now.